Featured Projects
Warehouse & Office Move
Relocated offices and a 250,000 sq ft warehouse at 1521 Greens Road to a new 400,000 sq ft warehouse at 1101 Conroe Park W. in Houston. Moved 10,000 pallets of toilet paper and paper towels and transported 22 embosser cylinders via flatbed tractor trailers. After the move, fully restored the origin warehouse to its original move-in condition — repairing dock levelers, repairing 38 bay doors, replacing 49 damaged bay door sections, repairing the concrete floor after removing 5,000 studs and anchors, cleaning 4 inches of paper dust off rafters and the entire warehouse, removing 700 feet of water line, exterior signage, security systems, network wiring, and forklift charging stations, and replacing damaged sheetrock, patching, and painting walls throughout the warehouse and offices plus the exterior.
A massive dual-scope project: relocating 10,000 pallets and 22 heavy embosser cylinders requiring flatbed tractor trailers to a facility 60% larger, then fully restoring the 250,000 sq ft origin warehouse — including 5,000 concrete stud/anchor removals, 38 bay door repairs, 49 bay door section replacements, and cleaning years of accumulated paper dust from rafters.
Developed a detailed project calendar with milestone tracking and regular check-ins. Coordinated flatbed tractor trailers for the 22 embosser cylinders, systematic pallet relocation for 10,000 pallets, and a full office move. After relocation, executed a comprehensive restoration of the origin warehouse — dock leveler and bay door repairs, concrete floor restoration, paper dust removal from rafters, removal of all utilities (700 ft of water line, security, network wiring, charging stations), and full interior/exterior paint and sheetrock work.
All 10,000 pallets, 22 embosser cylinders, and office contents relocated to the new 400,000 sq ft facility, and the origin 250,000 sq ft warehouse fully restored to original move-in condition — dock levelers repaired, 38 bay doors serviced, 49 door sections replaced, 5,000 studs removed, and the entire facility cleaned, patched, and painted.
Office Move
Relocated 700 employees across 9 floors from 700 Milam to 845 Texas Ave in an 11-phase move. Delivered 700 crates to every office, cubicle workstation, and common area across all 9 floors, then executed a strategic floor-by-floor game plan to move all labeled items within a tight timeline. ~20 truckloads and 1,411 items total.
Strict deadline to vacate the existing lease with zero tolerance for downtime at a Fortune 500 energy company — coordinating 700 employees across 9 floors with 1,411 items and 700 crates.
Executed an 11-phase weekend move plan with dedicated IT migration crews and project managers on both sites. Strategically delivered and collected 700 labeled crates floor-by-floor to ensure every item reached its correct destination.
Zero business downtime — all 700 employees returned Monday morning to fully operational workstations.
Warehouse Move
Relocated a 100,000 square foot warehouse operation involving 200–250 truckloads using 52-foot trailers over a 14–25 day timeline. Moved heavy cabinetry inventory, pallet racking, and warehouse equipment to the new facility.
Massive volume of heavy cabinetry product requiring 200–250 full 52-foot trailer loads, with strict inventory tracking across thousands of SKUs over a multi-week operation.
Developed a detailed logistics plan with dedicated trailer staging, systematic rack-by-rack disassembly, and SKU-level inventory tracking throughout the entire 14–25 day operation.
All inventory accounted for with zero product damage — the new 100,000 sqft warehouse was fully operational on schedule.
Warehouse Move
Relocated ~60 employees in a massive 75,000 square foot warehouse move involving 5,394 items — primarily 2,697 pallets — across ~674 truckloads using 53-foot trailers. Included 4 shrink wrap machines, metal shelving disconnect/reconnect, and 337 Comp-U-Wraps.
An enormous volume of 2,697 pallets and 5,394 total items requiring ~674 truckloads, plus 4 industrial shrink wrap machines and metal shelving systems that all needed to be moved without disrupting operations.
Deployed 4 pallet jacks, 2 additional forklifts on a 9-day rental, and a phased logistics plan to systematically move 674 trailer loads. Handled metal shelving disconnect/reconnect and wall board relocation with dedicated teams.
All 5,394 items and 2,697 pallets relocated with zero inventory loss — the warehouse was fully operational at the new facility on schedule.
Office Move
Relocated 300–350 employees in a large-scale 75,000 square foot office move from 6100 Hillcroft to 13501 Katy Fwy spanning 7 floors. Handled 1,038 items across 4 truckloads including 600 bubble-wrapped monitors and specialized lab equipment.
Sensitive geotechnical testing equipment and 600 monitors across 7 floors required specialized handling, bubble-wrapping, and climate-controlled transport.
Custom-built crating for lab equipment, climate-controlled vehicles, individually bubble-wrapped all 600 monitors, and deployed a dedicated equipment calibration team post-move.
All sensitive equipment and 600 monitors arrived without damage; lab was recertified within 48 hours of move completion.
Office Move
Relocated ~200 employees across multiple locations (HQ, Hunters Creek, and Conroe) totaling 52,000 square feet. Managed 1,423 items across ~8 truckloads including full cubicle and monitor arm deinstallation and reinstallation.
Complex modular furniture systems with cubicles and monitor arms needed to be deinstalled, transported across multiple locations, and reconfigured to completely different floor plans.
Partnered with the furniture manufacturer's certified installers and created detailed labeling and mapping systems. Coordinated simultaneous crews across HQ, Hunters Creek, and Conroe locations.
All 200+ workstations across 3 locations reassembled and operational with no missing parts or damage claims.
Office Move
Relocated 150–250 employees in a multi-floor office move spanning 4 days. Managed ~1,541 items across ~18 truckloads with 500 crates and 580 Comp-U-Wraps for monitor and electronics protection.
Massive item count across multiple floors with hundreds of monitors and electronics requiring individual protection — all within a tight 4-day window to minimize business disruption.
Deployed 500 crates and 580 Comp-U-Wraps for comprehensive electronics protection. Executed a phased floor-by-floor plan with 18 truckloads strategically sequenced to keep the move on schedule.
All 1,541 items and 580 wrapped electronics delivered without damage — employees returned to fully operational workstations on schedule.
Internal Office Relocation
Executed a 2-phase internal office relocation across the 9th and 12th floors at 9805 Katy Fwy. Managed 381 items with 212 crates, 120 Comp-U-Wraps, and 65 PC bags. PC techs disconnected and bubble-wrapped 100–108 monitors before the moving crew transported all items to their designated offices.
Multi-floor internal move requiring precise coordination between PC tech teams and movers — every monitor needed individual bubble-wrapping, disconnect, and reconnect across two non-contiguous floors.
Deployed a 2-phase plan: Phase 1 on Friday afternoon for crate and monitor transport with 4 PC techs and a moving crew; Phase 2 on Saturday morning with 7 PC techs for full monitor reconnection, quality checks, and a final client walkthrough.
All 381 items and 108 monitors delivered and reconnected — Murphy Oil was fully operational by Saturday afternoon.
Warehouse Move
Relocated 40–50 employees in a combined office and warehouse move in Baytown across 3 phases. Handled 28 bays of pallet racking, 3 industrial machines, and ~9.4 truckloads of equipment and inventory.
Heavy industrial racking (28 bays), 3 large machines, and thousands of catalogued parts needed to maintain inventory accuracy during a 3-phase transit.
Barcode-scanned every pallet and bin, disassembled all 28 bays of racking with structural engineers on-site, safely rigged 3 industrial machines, and reassembled everything at the new Baytown facility.
100% inventory accuracy confirmed post-move with zero loss or misplacement across all 3 phases.
Medical Decommission & Office Relocation
A two-phase, multi-city project spanning RediClinic's Houston HQ office relocation and the full-scale decommission of all 36 RediClinic locations inside H-E-B stores across Houston, Austin, and San Antonio. When Rite Aid abruptly shut down every RediClinic in Texas on August 13, 2020 — in the middle of the COVID-19 pandemic — Corporate Relocators deployed 4 crews simultaneously to begin IT equipment removal across 22 Houston-area locations, then continued through Austin and San Antonio. The scope included removing all interior and exterior signage (backlit channel letters, Lexan panels, street pylons, 40 mounted TVs, 36 wall-mounted tablets, 90 framed signs), stripping vinyl wall graphics at 20 locations, removing all furniture, medical equipment, and supplies, shipping servers to Rite Aid's corporate office, constructing walls and doors at 33 locations, and restoring every clinic to white box condition — all coordinated store-by-store with H-E-B management across 21 cities.
Decommissioning 36 medical clinics inside active H-E-B grocery stores across 21 cities and 3 metro areas — each requiring OSHA-compliant scaffolding, boom lifts, and scissor lifts for signage removal while maintaining safe conditions for store customers and staff. Every location had unique signage configurations, wall damage unknowns beneath vinyl graphics, and required individual coordination with H-E-B store managers. RediClinic had served nearly 1.5 million patients since 2005 before Rite Aid's sudden closure.
Deployed 4 simultaneous crews for rapid IT equipment removal across all Houston locations on Day 1, followed by a systematic 2-locations-per-day schedule for signage removal and decommission across all 3 markets over 30 days. Used ladder trucks and boom lifts for exterior signage, OSHA-approved scaffolding for interior work, and 3M blockout vinyl film on shared street pylons to avoid replacing other tenants' graphics — a significant cost savings for H-E-B. Coordinated wall and door construction at 33 locations to restore the sales floor to white box condition.
All 36 RediClinic locations across Houston, Austin, and San Antonio fully decommissioned — signage removed, furniture and medical equipment cleared, IT equipment shipped to Rite Aid, vinyl graphics stripped, walls and doors constructed at 33 locations, and every clinic restored to white box condition, on schedule and coordinated with H-E-B across 21 cities.
Furniture Relocation
Relocated furniture and workstations for ~50 employees at Sullins, Johnston, Rohrbach & Magers across 10,000–12,000 square feet. A 14-installer furniture team handled full deinstallation and reinstallation over 4 days.
Complex modular furniture systems required professional deinstallation and precise reinstallation to a new floor plan — all within a 4-day window.
Deployed a 14-person certified furniture installation team for systematic deinstallation, transport, and reinstallation coordinated with the new space's floor plan.
All workstations for 50 employees fully reassembled and operational — zero furniture damage or missing components.
Office & Warehouse Move
Relocated 15–30 employees in a combined office and warehouse move totaling 5,000–10,000 square feet. Managed 353 items with 140 crates across ~4.5 truckloads.
Combined office and warehouse move required handling both sensitive office electronics and heavy warehouse equipment with different transport and protection needs.
Separated office and warehouse phases with dedicated teams for each. Used 140 crates for office items and specialized equipment handling for warehouse materials.
Both office and warehouse fully operational post-move with all 353 items accounted for and zero damage claims.
Medical Office Move
Relocated a dermatology and laser surgery practice from 6400 Fannin St in the Texas Medical Center area to 1802 Binz St in Houston across a 3-phase, 2-day move. Managed 323 items — including 100+ pieces of medical equipment — with 95 crates, 30 Comp-U-Wraps, and 20 commercial bins across ~5 truckloads. Ceiling-mounted medical devices were deinstalled by certified installers, individually padded, and packed into designated containers. All medical cabinets, exam stools, medical carts, IV poles, gondolas, and laser equipment were bubble-wrapped and stretch-wrapped before transport.
Over 100 pieces of sensitive medical and laser equipment — including ceiling-mounted devices requiring specialized deinstallation — all needed to be carefully protected, transported, and reinstalled at the new practice without damage or calibration loss.
Executed a 3-phase plan: Phase 1 on Friday afternoon for pre-move preparation — deinstalling ceiling-mounted medical devices, padding and packing all equipment. Phase 2 at 5 PM loaded 3 trucks and staged everything at the new space. Phase 3 on Saturday morning with a full crew set up furniture and medical equipment room-by-room while installers reassembled ceiling-mounted devices. A final walkthrough confirmed every room was properly set up.
All 323 items — including 100+ pieces of medical equipment and ceiling-mounted laser devices — relocated, reinstalled, and fully operational at the new practice with zero damage.
Veterinary Medical Office Move
Relocated a veterinary emergency clinic from 8921 Katy Fwy to 8731 Katy Fwy in Houston across a 2-phase, 2-day move. Managed 332 items with 140 crates, 45 Comp-U-Wraps, and 30 commercial bins across ~4 truckloads. The move included specialized medical equipment — 4 medical carts, 3 IV poles, 10 medical stools, 9 medical cabinets, and a PT bed — all requiring individual padding, bubble-wrapping, and stretch-wrapping. A construction crew disassembled and transported 6 stainless-steel lavatories (including plumbing and electrical) and 6 exam beds with cabinets, then reinstalled everything at the new location.
A veterinary medical facility with sensitive equipment, stainless-steel lavatories requiring plumbing and electrical disconnection, and the need to keep the clinic partially operational during Phase 1 while critical equipment remained in place.
Executed a 2-phase plan: Phase 1 moved the bulk of medical equipment, furniture, and electronics while leaving essential items in place for continued operations. Phase 2 relocated remaining items, reinstalled 6 lavatories with plumbing and electrical, mounted all TVs and monitors, and completed PC/printer reconnections. A final walkthrough confirmed every item was in place.
All 332 items — including medical equipment, 6 stainless-steel lavatories, and exam beds — relocated, reinstalled, and fully operational at the new facility with zero damage.
Office Move
Relocated 9–20 employees within the same building, managing 486 items with 125 crates and 70 Comp-U-Wraps across ~4 truckloads. Handled full cubicle and workstation relocation.
Same-building moves require precise coordination with building management, elevator scheduling, and minimizing disruption to other tenants — all while protecting 486 items.
Coordinated closely with building management for dedicated elevator access and loading dock time. Deployed 125 crates and 70 Comp-U-Wraps for systematic packing and protection.
All 486 items relocated within the building with zero damage — employees returned Monday to fully set-up workstations.
Office Move
Relocated 8–15 employees in a compact office suite move of 2,000–4,000 square feet. Managed 165 items with 55 crates and 30 Comp-U-Wraps across ~3.4 truckloads.
Small team with tight timeline required the same level of care and project management as a large-scale move — every item critical to a lean operation.
Assigned a dedicated project manager and deployed 55 crates and 30 Comp-U-Wraps. Executed a streamlined single-phase move plan tailored to the compact footprint.
All 165 items delivered and set up with zero downtime — the team was fully operational Monday morning.
Free Walkthrough
Tell us about your move and we'll reach out within a few hours to schedule a walkthrough. No pressure, no commitment.

"Excellent customer service and great communication throughout our move. Will definitely be using them again!"
A team member will call or text to confirm your walkthrough time.
We visit your current space and your new space to get an accurate picture of everything involved.
Full breakdown: inventory, truckloads, all rates. Nothing vague, nothing hidden.
No pressure. Most clients get 3–4 bids. We're confident in our proposal.
Trusted by Houston's largest companies
WBENC · WOSB · HUB · BBB A+
Certified for Fortune 500 and government procurement
What you get, free